Tuesday, October 1, 2024

Baghdad

MoE, French Co. discuss progress in Mosul 400 kv station

 

Baghdad (IraqiNews.com) The Directorate General of the electric power transmission projects discussed with the French Alestom Company, the mechanism and means of implementing the Mosul Sub-Station Transformational project with a capacity of 400 KV, which will hopefully be starting out at the end of 2012.

The Spokesperson of the Ministry Musab al-Mudaris clarified “This project aims to relief the load in the national network and to increase its reliability in Mosul province.”

The MoE had contracted with the company on last September to implement the project at a cost of 660 million Euros on Late Payment system which includes processing and erecting equipments as well conducting engineering and electric activities within 24 months execution duration.