Substation rehabilitated in Basra
BASRA / IraqiNews.com: A local company on Wednesday finalized the project of supplying and installing a power substation at al-Gzayza area, with a total cost of $3.35 million, according to the director of Basra rebuilding unit. “Work continued for six months to finalize the project,” Engineer Ziyad Ali Fadhil told IraqiNews.com. “The project will improve power transmission in the area and nearby areas,” he added. The oil-rich city of Basra lies 590 km south of Baghdad. MH (P)/ SH 1